PMP考试模拟题(28个)


    Sample Professional Responsibility exam questions

    1  While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract You should
    a Honor the customer's request as sign of cooperation to ensure future business
    b Refuse the request and report the customer to your sponsor
    c Acknowledge the request and advise the customer to submit a formal change request
    d Convene a meeting of the project team and rewrite the scope statement
    2 You are managing an internal R&D project The initial test results are very poor You are afraid your management might cancel the project and this could reflect poorly upon you Verification testing could be done quickly and inexpensively You should
    a Be the first to recommend canceling the project
    b Inform management about the results and wait for a response
    c Inform management immediately and recommend retesting for verification
    d Withhold the information from management until you perform additional tests to verify the initial results
    3 During an informal meeting with your project client you are offered a substantial monetary incentive to alter the configuration of the product to meet the client's personal need This change may result in additional project costs and schedule delays The appropriate action to take would be
    a Refrain from accepting the offer and advise the customer to submit a request to the change control board
    b Accept the offer and issue an internal configuration change request to the design group
    c Obtain additional information about the request and the customer's personal need before accepting the offer
    d Delay acceptance of the offer until you can ensure that you can protect yourself from any legal liabilities
    4 As the project manager for a very large and highly visible project you receive a preliminary press release for your approval before distribution You are expected to approve the release without comment Your review identifies a major discrepancy regarding some key project financial estimates that may mislead the intended recipients As the project manager it is your responsibility to
    a Inform the project sponsor of the discrepancy and refuse to approve the release
    b Approve the release but send a memo to the sponsor advising that you are aware of the discrepancy and will refer any questions your receive to the sponsor
    c Completely rewrite the press release and include the correct information
    d Approve the release as requested
    5 Your project is running out of cash and significant work remains You are directed by senior management to instruct your people to use another project's charge numbers while working on your project You should
    a Follow instructions
    b Inform the corporate auditors
    c Understand the background of management's instructions before taking any action
    d Shut down the project if possible
    6 While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects You should
    a Reject the estimate and remove the functional manager from the project
    b Request the supporting details for the estimate to ensure it has been properly prepared
    c Accept the estimate and plan to use the additional funding as a reserve
    d Question each functional manager for information about this estimate
    7 You are working in a country where it is customary to exchange gifts between contractor and customer Your company code of conduct clearly states that you cannot accept gifts from any client Failure to accept the gift from this client may result in termination of the contract The action to take in this case would be
    a Provide the customer with a copy of your company code of conduct and refuse the gifts
    b Exchange gifts with the customer and keep the exchange confidential
    c Contact your project sponsor and or your legal or public relations group for assistance
    d Ask the project sponsor or project executive to exchange gifts
    8 During your assignment as project manager you add a new member to your project team This new team member was recently hired from a competitor and offers to share a substantial amount of proprietary information from his previous company This information could put you and your team in a very strong position for future business You are aware of a non compete clause in the new hire's condition of employment You should
    a Accept the information and agree to keep it confidential between you and the new hire
    b Review the condition of employment with the new hire and advise her to reconsider the offer
    c Review the information and only accept only what may have a direct impact on the project's financial status
    d Ignore the offer to share and move forward with the project
    9 You are asked to write a paper for your sponsor so that heshe can present it at a technical meeting You are informed that hisher name will be the only name on the paper You should
    a Follow instructions
    b Follow instructions but demand that your name also appears
    c Refuse to follow the instructions
    d Go over the head of your sponsor seeking advice
    10 An example of a conflict of interest would be
    a As a public official you make a decision about a contract award that will benefit you personally
    b You and a functional manager disagree with a task cost estimate
    c Your sponsor decides to cancel your project because it no longer supports the company strategy
    d Your personality conflicts with that of a key member of your project team
    11 Each of the following describes the use of an ethical approach except
    a Attempting to understand the religious and cultural sensitivities of the country in which you have been assigned
    b Ensuring that personal interest does not interfere with your decision making process
    c Accepting gifts in exchange for favoring one contractor over another
    d Maintaining confidentiality of sensitive information obtained during the project life cycle
    12 To maintain the customer's schedule massive overtime will be required between Christmas and New Years Many of your team members have put in for vacation during this time You should
    a Let the schedule slip and inform the customer
    b First give the employees the choice of working overtime
    c Make the employees cancel their vacation plans and work overtime
    d Hire temporary employees for the overtime
    13 Which of the following situations describes a violation of the PMPProfessional Code of Conduct
    a Accepting a gift that is within the customary guidelines of the country or province you are currently working in
    b Use of confidential information to advance your position or influence a critical decision
    c Complying with laws and regulations of the state or province in which project management services are provided
    d Disclosing information to a customer about a situation that may have an appearance of impropriety
    14 In order to balance the needs of the many stakeholders involved in your project the most desirable method to achieve resolution of conflicts would be
    a Compromise
    b Forcing
    c Controlling
    d Confrontation
    15 You receive a contract to perform testing for an external client After contract award the customer provides you with the test matrix to use for your 16 tests The vice president for engineering says that the customer's test matrix is wrong and she will use a different test matrix which should give better results This is a violation to the SOW Suppose your sponsor is also the vice president for engineering You should
    a Use the customer's test matrix
    b Use the engineering test matrix without telling the customer
    c Use the engineering test matrix and inform the customer
    d Tell your sponsor that you want to set up a meeting with the customer to resolve the conflict
    16 In order for the project manager to fully and effectively understand a stake holder's personal concerns or grievances it may necessary to
    a Ask for a written description of the problem and submit it through the project office
    b Schedule a project review session with the entire project team
    c Attempt to empathize with the stakeholder
    d Involve the project sponsor as an arbitrator
    17 As the leader of a project team the project manager may be required to assess the competencies of his or her team members Occasionally some weaknesses or areas for improvement will be identified The project manager should
    a Remove any team members who have demonstrated weaknesses in critical knowledge areas
    b Communicate those weaknesses and establish a performance improvement program
    c Hire additional resources to compensate for weak areas
    d Wait for the team members to fail in an assignment to justify termination
    18 You have just changed jobs and discovered that your new employer routinely violates OSHAEPA and affirmative action requirements on projects You should
    a Do nothing it's not your problem
    b Start by asking management if they are aware that regulations are being violated
    c Talk to the corporate legal department
    d Inform the appropriate government agencies about the violations
    19 The project manager must be an effective communicator to ensure that project stakeholders receive and understand project related information and status Prior to delivering information to the stakeholders the project manager should attempt to
    a Research and understand the region of experience of the stakeholder before transmitting information
    b Identify only those stakeholders that have a the same background experience as the project manager
    c Filter the information to remove any details
    d Restrict information to specific technical details
    20 As part of your project plan you must develop an effective method of communication for your multinational team of stakeholders You have several choices of media available The appropriate action to take in the development of the communication plans would be to
    a Discuss the available options with the stakeholders and obtain their input
    b Use the standard media that has been in effect for your previous projects
    c Use multiple forms of media to ensure that everyone receives the information
    d Obtain additional funding from the project sponsor and develop a project specific communications infrastructure
    21 One of your employees is up for promotion If the promotion is granted the employee will be reassigned elsewhere causing a problem for you on your project You can delay the promotion until your project is completed You should
    a Support the promotion but work with the employee and the employee's new management to develop a good transition plan
    b Ask the employee to refuse the promotion until your project is completed
    c Arrange to delay the promotion until the project is completed
    d Tell the employee that it is his responsibility to find a suitable replacement so that the project will not suffer
    22 The integrity of the project manager is often challenged by stakeholders who attempt to use personal power or influence to change the scope of an agreed upon deliverable In these situations the project manager's most appropriate response would be
    a Refer the stakeholder to the process for change documented in the approved contract
    b Agree to the change because customer satisfaction is the goal regardless of cost
    c Contact the legal department and suspend all further project work
    d Determine the risks and rewards for implementing the change before taking any action
    23 During project implementation the client interprets a clause in the contract to mean the he is entitled to a substantial refund for work recently completed You review the clause and disagree with the client's conclusion As the project manager which of the following actions should be taken
    a Disregard the customer's conclusion and continue to process invoices
    b Document the dispute and refer to the provisions of the contract that address interpretations and disputes
    c Advise the customer that ambiguous information in contracts is always interpreted in favor of the contractor
    d Immediately correct the clause to remove any possible misinterpretation by the customer
    24 Your executives in appreciation for the success of your project have given you a 10000 bonus to be disbursed among your fiveteam members One of the five who is a substandard worker and accomplished very little on your project is in your car pool You should
    a Provide everyone with an equal share
    b Provide everyone a share based upon their performance
    c Ask the workers to decide among themselves how the bonus should be subdivided
    d Ask the sponsor to make the decision
    25 Before reporting a perceived violation of an established rule or policy the project manager should
    a Determine the risks associated with the violation
    b Ensure there is a reasonably clear and factual basis for reporting the violation
    c Ignore the violation until it actually affects the project results
    d Convene a committee to review the violation and determine the appropriate response
    26 Project Managers can contribute to their organization's knowledge base and to the profession of project management most effectively by
    a Developing and implementing a project review and lessons learned process
    b Establishing strict guidelines for protecting intellectual property
    c Promote the use of ad hoc project management
    d Ensuring that all project plans are developed before the project team is formed
    27 You have been assigned two concurrent projects Because of the nature of the projects you have a conflict of interest You should
    a Do the best you can and tell no one
    b Ask to be removed from one of the projects
    c Ask to be removed from both of the projects
    d Inform your sponsor and ask for his advice
    28 You receive a contract to perform testing for an external client After contract award the customer provides you with the test matrix to use for your 16 tests The vice president for engineering says that the customer's test matrix is wrong and she will use a different test matrix which should give better results This is a violation to the SOW You should
    a Use the customer's test matrix
    b Use the engineering test matrix without telling the customer
    c Use the engineering test matrix and discuss the reasons with the customer
    d Ask your sponsor for clarification assuming that the vice president is not your sponsor
    29 An effective method for improving an organization's project management knowledge base is through
    a Coaching and mentoring
    b Referent power
    c A weak Matrix organizational structure
    d Fast Tracking

    Answer Key
    1c
    8b
    15d
    22a
    2d
    9b
    16c
    23b
    3a
    10a
    17b
    24c
    4a
    11c
    18b
    25b
    5c
    12b
    19a
    26a
    6b
    13b
    20a
    27d
    7c
    14d
    21a
    28d



    29a


    文档香网(httpswwwxiangdangnet)户传

    《香当网》用户分享的内容,不代表《香当网》观点或立场,请自行判断内容的真实性和可靠性!
    该内容是文档的文本内容,更好的格式请下载文档

    下载文档到电脑,查找使用更方便

    文档的实际排版效果,会与网站的显示效果略有不同!!

    需要 2 积分 [ 获取积分 ]

    下载文档

    相关文档

    PMP考试模拟题(28个)

    Sample Professional Responsibility exam questions1.  While working on an external project your c...

    10年前   
    594    0

    PMP考试学习心得

    PMP考试学习心得  我几乎都是利用自己的业余时间进行PMP和项目管理学习的,一般都在项目上很忙,时间时非常的宝贵的,我最初就是这样计划的,一定找一家让我省力气的、高效的培训班,这样我投入的精...

    12年前   
    437    0

    PMP考试的100个关键点

    1. 一个项目在启动阶段会进行量级估算,准确范围是-50至100%。2000版的量级估算准确度为:-25%到+75%。 参考:PMBOK2004 P161 CH P137 7.1 成本估算。 ...

    12年前   
    460    0

    2002年PMP考试的一些信息

              2002年PMP考试的一些信息一、2002年PMP考试日期表考试日期3月23日6月22日9月21日12月7日报名截止日期1月15日4月12日7月12日9月30日提交材料截止...

    14年前   
    459    0

    PMP考试模拟试题(40题)

    考前模拟试题 Disclaimer: These questions are intended for study purposes only. Success on these quest...

    12年前   
    645    0

    PMP考试技巧24计

    PMP考试技巧24计 第1计 先调查,后决策例1:在新公司,你发现公司的一些财物报告没有遵照会计准则,所以并不准确,在这种情况下,你首先要做的是? A、将公司不准确的记账操作通知政府B、与你...

    9年前   
    455    0

    PMP项目管理模拟考试卷——17-成都模拟题

    1. To help the project team function more efficiently on complex and interrelated tasks, the pro...

    12年前   
    440    0

    PMP项目管理模拟考试卷——18-成都模拟题答案

    模拟题答案1C21C41D61C81C2C22D42D62B82A3B23D43B63A83A4A24B44D64A84B5A25B45C65C85B6B26A46A

    10年前   
    605    0

    pmp学习心得

    pmp学习心得第一篇:pmp学习心得pmp考试心得三个月紧张而富挑战的pmp备考结束了, pmp考试也是一个理顺项目管理思路的过程,在知识点,尤其是职业道德的理解上要以pmp思路对待,重要的是...

    10年前   
    510    0

    PMP学习心得

    PMP学习心得  我参加的XX年1月的培训班,3月23日考试。成绩不算高但庆幸通过了,回顾整个学习,复习,考试各阶段,把自己的经验教训总结分享给各位同学。  01. 提前报名,课前通读一遍。 ...

    10年前   
    603    0

    PMP项目管理模拟考试卷——5-科兹纳PMP模拟试卷

    概述1、项目是一系列——的活动和任务。A、具有特定目标。B、具有明确开始和终止日期。C、资金有限(如果可用)。D、消耗资源。E、以上皆是。2、成功的项目管理可以被定义为——达到了项目管理目标。...

    12年前   
    973    0

    PMP道德规范

    PMI MEMBER ETHICAL STANDARDSMEMBER CODE OF ETHICS The Project Management Institute (PMI) is a pr...

    9年前   
    468    0

    一次性成功通过PMP考试的备考经验交流

    一次性成功通过PMP考试的备考经验交流  一、选择学习的方式  在短暂紧张的应考时间里,如何顺利通过PMP的考试?这就要在考试前做好充分的考前时间安排,做好应试的学习与复习计划。最好的应试策略...

    11年前   
    447    0

    PMP应试六步法

    1、 我们既然决定要去考 PMP,那就要做一些前期准备工作了,我自己事先在网上看一些关于 PMP 的一些资料,当然这些都是先了解一下,比如:什么是 PMI 协会、有关 PMP考试的相关信息、P...

    10年前   
    669    0

    PMP Preparation Overview Updated for PMBOK 2000

    PM AreaArea ProcessImportant Tools and TechniquesMajor Deliverables (Outputs)Process GroupOther ...

    14年前   
    618    0

    PMP培训学习心得

    PMP培训学习心得  section 1学习篇  pmp考试不是你背书有多厉害就能通过,而是重在理解。考试能获得越多的p,说明你对项目管理的理解就越接近pmi的思维理念。  两个月时间内,平均...

    10年前   
    501    0

    PMP和PRINCE2的价值所在

    PMP和PRINCE2的价值所在  我是项目管理专职讲师,很多学员朋友会问我同样的问题:“PMP和PRINCE2到底有什么区别?哪个含金量更高?”看来,这是所有要参加认证的朋友普遍关心的问题,...

    12年前   
    533    0

    PMP项目管理模拟考试卷——22-IPMA C级试卷

    华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA C级 应试人员: 准考证号: 分...

    12年前   
    689    0

    PMP项目管理模拟考试卷——23-IPMA D级试卷

    华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA D级 应试人员: 准考证号: 分...

    12年前   
    1027    0

    PMP项目管理模拟考试卷——16-2004.模拟考试试题

    1. What are the 4 stages of team development?a. Assignment, kick-of, training, communicatingb. F...